Ukraine approved a mechanism for using nearly UAH 939 million from the Finland–Ukraine Investment Facility for four distributed-generation projects implemented by Ukrnafta.
Planned projects
- Four gas-piston power plants are planned in the Ivano-Frankivsk and Lviv regions.
- The projects are expected to add approximately 60 MW of capacity to Ukraine’s energy system.
- Ukrnafta will procure the plants and auxiliary equipment and handle installation, testing and commissioning.
Financing and implementation
The funds are credit resources raised for the state budget under a 2024 framework agreement between Finland and Ukraine. Approval of the financing mechanism does not mean all four plants are already operating; procurement, installation and commissioning still have to be completed.